Reason for Affected our Look Ahead program
Date: xxx
Ref. xxx
To:
M/s. xxx Consulting Architects and Engineers
Dubai, UAE
Kind Attn: Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai.
Subject: Reason for Affected our Look Ahead program
Dear Sir,
Due to following changes in drawing, our weekly Look ahead program affected
- De-watering pit design changes, we need to do the RCC Wall instead of Block Work including water tank area.
- Once again drawing changed for Tower crane Location at Basement –II level.
- Balance Raft area affected due to drawing changing for dewatering pit No (1,2&3).
- As per instructed by DM we excavated 1500mm wide trench at around the water tank block work wall South-west side (Grid Plot limit –D / 04-06 )
Note : Due to above reason our progress is dealy, this is for your kind information & record
Regards,
For xxx Contracting L.L.C
xxx
Project Manager
Md Abu Zaed Khan