Order confirmation to transformer shifting and other DEWA scope

Order confirmation to transformer shifting and other DEWA scope

Date: xxx

Ref: xxx

To                 : Total , Dubai, UAE

Project          : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai

Subject: Order confirmation to transformer shifting and other DEWA scope

Dear Mr. xxx,

With respect to your quotation ref 104118/QTN/CCL/TEM/DG/10022018 send on 01/03/xxx with following scope, terms and conditions as required by DEWA and their approval

A) Scope of work as agreed

  • Collecting of cable drum from DEWA store
  • Transportation of cable drums to site
  • Pulling of cable
  • Supply & fixing of cable cleats, cable ties, etc
  • Dressing of cable
  • Returning of empty drums to DEWA store
  • Coordination with DEWA
  • Shifting of transformer from outside the building to substation room
  • Insurance for transformer shifting

B) Cost of work

The lump sum cost for the scope mention above which include pulling of   cable, supply & fixing of cable cleats, cable ties, etc, dressing of cable, insurance for transformer shifting along with DEWA transformer and NOCs

AED 23,000 + Vat (AED 1,150) = AED 24,150 (twenty four thousand one hundred and fifty)

C) Duration of work from advance payment

2 to 3 weeks (Maximum)

D) Payment terms and conditions

50% advance with company guarantee Cheque

Balance after handling over the work as per DEWA norms and acceptance by DEWA and inspection report from DEWA/ their NOC

Thanks and Regards

xxx

Project Manager