Our Ref: xxx
Date: xxx
To : xxx Contracting Middle East,
Related posts:
Abortive Works to Structural Slab for Pod Drainage Penetration
Response Against Benchmark Room 24 Snag Consultant Comments.
P.O.Box xxx,
Dubai, UAE
Attention : Ms. xxx
: Project Director
Project : xxx Tower Views, Dubai
Subject : Conformance letter for laminate Pattern cut
Dear Mr. Mohsin,
With reference to the above subject and Project, for obtaining Material approval xxx have to submit a conformance letter from the supplier/manufacturer to the contractor stating that “non-availability of quarter cut in Millennium (F5887) Oak and Delano Oak (F8966)’.
Please consider this request with high priority and do the needful at the earliest.
Thanks,
Thanks.
Yours faithfully,
On behalf of xxx LLC
xxx
Project Manager