Regarding submission of the revised drawing received for Signage from consultant with the coordination with your shop drawing.
Date: xxx
CC/DANWAY/06
To: M/s xxx LLC
Att’n: The Manager
Project: 2B + G + 14 + Lower Roof Hotels Building, Plot No. 373-1297 at Al Barsha 1st, Dubai
Subject: Regarding submission of the revised drawing received for Signage from consultant with the coordination with your shop drawing.
Dear Sir,
With reference to the above mentioned subject, we are attaching the revised drawing received from consultant for signage and kindly note the following.
- Submit the shop drawing of the cradle by incorporating the signage position to coordinate for your cradle shop drawing.
- If any impact for your equipment or cost variances kindly submit accordingly.
- Also provide power requirement and power layout drawing to incorporate in our electrical drawing.
So, this is for your kind information and do the needful as you have been coordinate with consultant.
This is for your action and acknowledgment as well as reply.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager
Md Abu Zaed Khan
0
Tags :