Impact on the progress of Slab no.13 due to high wind speed

Impact on the progress of Slab no.13 due to high wind speed

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E

Sub   :                Impact on the progress of Slab no.13 due to high wind speed on dated xxx and rain on dated xxx

Dear Sir,

With reference to the above, we would like to inform you that, slab work of 13th floor is totally interrupted and under hold due to following reasons and on the days described:

1) On dated 20.03.17, there was a high wind speed of 37km/hrs, which is double of the working speed.

2) There was overnight rain on dated 20.03.17,  which is still continued, due to which we cannot operate tower crane and cut off of all supply lines which are leading to the roof to avoid fire hazard.

So, this is for your kind intimation that slab work is being delayed due to unfavorable weather condition.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *