Regarding the front entrance glazing support fixing before false ceiling

Regarding the front entrance glazing support fixing before false ceiling

Date: xxx

Ref. xxx

To:                     M/s. xxx , Metal Wowks

Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject           : Regarding the front entrance glazing support fixing before false ceiling

                          By Makstylo and submission of revised shop drawing for revolving door

                          Area

Dear Mr. Raphael,

We are hereby informing you that our false ceiling work is in progress at ground floor entrance area and you have the coordination for curtain wall around the revolving door and supporting to ceiling concrete for curtain wall

            So, your previously submitted drawing was commented and not as per the revised floor plan and this has been discussed and intimated and till now, you did not submit the revised drawing.

Meantime, ceiling works is in progress and you will be facing lots of problem if you will not support as well as our ceiling height also reduced by 100mm. that also will be marked in shop drawing which is awaited from you.

Regards,
For xxx Contracting L.L.C

xxx

Project Manager