Removal of Roadside Scaffolding

Removal of Roadside Scaffolding

Date: xxx

Ref. xxx

To:                     M/s. xxx , Metal Wowks

Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject           : Removal of Roadside Scaffolding

Dear Mr. Raphael,

With reference to the above mentioned subject, we are hereby intimating you that we are removing the roadside scaffolding since RTA will start the external interlock and Dubai Municipality will execute the drainage connection because we are holding the authority to complete your work and now we cannot stop them to execute their work to complete the project as we have given 10 days by Dubai Municipality to clear the area.

So, we are informing you that we will remove the road scaffolding and you are allowed to use cradle.

Regards,
For xxx Contracting L.L.C

xxx

Project Manager