Date: xxx
Ref. xxx
To: M/s. xxx , Metal Wowks
Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai
Subject : Regarding the front entrance glazing support fixing before false ceiling
By Makstylo and submission of revised shop drawing for revolving door
Area
Dear Mr. Raphael,
We are hereby informing you that our false ceiling work is in progress at ground floor entrance area and you have the coordination for curtain wall around the revolving door and supporting to ceiling concrete for curtain wall
So, your previously submitted drawing was commented and not as per the revised floor plan and this has been discussed and intimated and till now, you did not submit the revised drawing.
Meantime, ceiling works is in progress and you will be facing lots of problem if you will not support as well as our ceiling height also reduced by 100mm. that also will be marked in shop drawing which is awaited from you.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager