Understand the given instructions

Eliminate the comments on shop drawing

Date: XXX

CC/SCHINDLER/002

To                   :  M/s XXX Intl.Ltd

Project            :  2B + G + 14 + Lower Roof Hotels Building, Plot No. XXX at Al Barsha 1st, Dubai

Subject           : Eliminate the comments on shop drawing

Dear Sir,

With ref to above, as we returned the lift drawing which is commented by consultant ,there are issues of LOP and their position (LOP and indicators above lintel).

Furthermore, you know the lift work is in progress, still your coordination drawings not approved and we are facing at site the issues to keep provision for LOP sizes and depth as well as the comments issued by consultant not incorporated.

Kindly look into this matter and do the needful.

Regards,

For XXX Contracting L.L.C

XXX

General Manager