Very serious issue may lead termination of the project or part of the project.

Date:               27.07.17 To                   : xxx Contracting Kind Attn        : Mr. xxx Project           : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject          :  Very serious issue may lead termination of the project or part of the project. Dear all concerned, With reference above, May face the termination of the project because […]

Regarding Confirmation and No –Objection to Remove the Tower Crane Support

Date:               xxx To                   : xxx Contracting Kind Attn        : Mr. xxx Vangani /Mr. xxx Project           : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject          :  Regarding Confirmation and No –Objection to Remove the Tower Crane Support @ 3rd Flr. and same System and Drawing can be used in  11th Flr. […]

Regarding material delivered and discrepancy By Future Formwork

Date:              xxx Ref:                 CC/AP/05/16 To:                   Mr. xxx/xxx/Mr.xxx Project:          2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:       Regarding material delivered and discrepancy By Future Formwork Dear Sir, With reference to the above mentioned subject and as per the invoice raised by the M/s Future Formwork we have […]

Submission of Original copy of Advance Bank Guarantee

Date:               xxx Ref:                  CC/AP/1801 To, Accounts section xxx Group              Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:           Submission of Original copy of Advance Bank Guarantee Kind Attn:Mr.xxx Dear Sir, With reference to the above, we are hereby submitting the advance payment bank guarantee to your […]

Meeting with project engineer Mr.xxx Bobde

Date:              xxx Project       :2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,      Dubai Attention      : Mr.xxx bobde, Project Engineer Subject         :  Meeting with project engineer Mr.xxx Bobde Sl no Description Action taken by Remarks 1 I Instructed to Mr.Prafulla To take all the material quantity for slab 9   a)ply   b)steel   […]

Regarding your meeting with the client and status update

Date:               xxx Ref:                  CC/269/LW/17 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:         Mayur Hingorani Project:            2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:           Regarding your meeting with the client and status update Dear Mayur,  With ref. to above, during most of our telephonic conversations we received from your end […]

Regarding delay in shop drawings submission and direct communication with the employer

Date:               xxx Ref:                 CC/269/LW/16 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:        Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding delay in shop drawings submission and direct communication     with the employer Dear Mayur, With ref. to above, still we are following up for the shop […]

Regarding issue related to submission of shop drawings for elevators

Date:               xxx Ref:                 CC/269/LW/15 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding issue related to submission of shop drawings for elevators Dear Mayur, With ref. to above, after long follow up you have sent the shop drawings […]

Regarding receipt of the advance payment against supply of elevators for Citymax, Al Barsha project

Date:               xxx Ref:                 CC/269/LW/14 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding receipt of the advance payment against  supply of elevators for Citymax, Al Barsha project Dear Mayur, With ref. to above, as we came to know […]

Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals

Date:               xxx Ref:                 CC/269/LW/13 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals Dear Mayur, With ref. to above, we would like to […]