Work order for Mineral wool panel with Al foil faced insulation (Rockwool)
Date: xxx
CC/269/CI/06
Kind Attn: The Manager, xxx Interior Division
Project: 2B + G + 14 + Lower Roof Hotel Building
Plot No. 373-1297 at Barsha, Dubai
Subject: Work order for Mineral wool panel with Al foil faced insulation (Rockwool)
Dear xxx,
With ref. to above, please note the following,
- Scope of work:
- Rockwool panel with aluminum foil faced insulation, installation from Fujairah rockwool – density= 45kg/m3 50mm thickness as per MR attached
- Rockwool panel to be fixed with PVC accessories and cap.
- GI grid to be prepared as per the section details attached
- The 12.5mm Gypsum board to be fixed on the grid next to rockwool with contact in perfect level
Area: 300sqm
Location: Basement-01
- Cost:
As per interdivision and company policy
- Schedule for execution :
Immediately and to be fixed within a week (Start and finish within 7 days)
- Contact details for clarification:
Mr.Ramlal Pareek- 0554714645
- General Notes:
- All materials to be delivered along with DO and specification details and inspection to be carried out prior to fixing by QA/QC Engineer – Alma and Consultant
- Safety induction to be carried out and workers must have PPE
Regards,
For xxx Contracting L.L.C
xxx
General Manager