To clear the pool deck area for foam concrete by tomorrow.

To clear the pool deck area for foam concrete by tomorrow.

Date: xxx

Ref. xxx

To                    : M/s xxx Trading Company

Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai

Sub                  : To clear the pool deck area for foam concrete by tomorrow.

Dear Sir,

We are here by strictly instructing you to clear the pool deck for foam concrete which we are going to execute on Thursday (25/1/18) morning.

So, you must clear any material from the pool deck and put inside the pool area. If you will hold our foam concrete it has a serious impact in our project.

This is for your kind information and do needful immediately without any further delay.

For xxx Contracting L.L.C

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *