Taking Over Service Lift and Submission of Third-party Certificate

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         : Taking over Service Lift and Submission of Third-Party Certificate for your record

Dear Sir,

Kindly find attached copy of inspection certificate issued by Elite Safety Consultants for the service lift, as a proof for the safety of the usage of service lift which is being handover by Schindler to the main contractor with rental cost under their maintenance and responsibility.

Related posts:
Regarding Location of Central Battery Rack
Delay in Approval of Steel Structure and Additional Cost

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager