Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Supply and installation of Façade lighting with nomination ref no:xxx
on dated xxx.
| SL NO | ITEM DESCRIPTION IN NOMINATION | CONTRACT BOQ ITEM REF | QTY | UNIT | RATE | AED | |
| 1 | Supply and installation of Façade Signage by a nominated sub contractor | Bill No12/2/5 | 1 | LS | xxx.00 | 72000.00 | |
| 2 | Allow for coordination builders work and over head profit | Bill No12/2/5 | 10 | % | xxx.00 | 7200.00 | |
| TOTAL AED | xxx.00 | ||||||
(Dirham: xxxx-nine thousand, two hundred only)
Related posts:
Cable Inside the Lift and Wifi and Camera Cable and Connection
Nomination for Internal Signage not Yet Provided
Attachments are attached herewith are,
1. Bills of Qunatities (BOQ)
2. Nomination letter ref no: AP/269/335 on dated 27/11/xxx
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager