Date:              xxx Ref:                 CC/AP/05/16 To:                   Mr. xxx/xxx/Mr.xxx Project:          2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:       Regarding material delivered and discrepancy By Future Formwork Dear Sir, With reference to the above mentioned subject and as per the invoice raised by the […]

Regarding material delivered and discrepancy By Future Formwork Read Post »

Advance Bank Guarantee

Submission of Original copy of Advance Bank Guarantee

Date:               xxx Ref:                  CC/AP/1801 To, Accounts section xxx Group              Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:           Submission of Original copy of Advance Bank Guarantee Kind Attn:Mr.xxx Dear Sir, With reference to the above, we are hereby submitting the advance

Submission of Original copy of Advance Bank Guarantee Read Post »

Elevator installation

Regarding your meeting with the client and status update

Date:               xxx Ref:                  CC/269/LW/17 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:         Mayur Hingorani Project:            2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:           Regarding your meeting with the client and status update Dear Mayur,  With ref. to above, during most of our telephonic conversations

Regarding your meeting with the client and status update Read Post »

calculate the variation from tender and revised drawing

Regarding delay in shop drawings submission and direct communication with the employer

Date:               xxx Ref:                 CC/269/LW/16 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:        Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding delay in shop drawings submission and direct communication     with the employer Dear Mayur, With ref. to above, still we are

Regarding delay in shop drawings submission and direct communication with the employer Read Post »

Elevator installation

Regarding issue related to submission of shop drawings for elevators

Date:               xxx Ref:                 CC/269/LW/15 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding issue related to submission of shop drawings for elevators Dear Mayur, With ref. to above, after long follow up you

Regarding issue related to submission of shop drawings for elevators Read Post »

Delayed of Salary

Regarding receipt of the advance payment against supply of elevators for Citymax, Al Barsha project

Date:               xxx Ref:                 CC/269/LW/14 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding receipt of the advance payment against  supply of elevators for Citymax, Al Barsha project Dear Mayur, With ref. to above,

Regarding receipt of the advance payment against supply of elevators for Citymax, Al Barsha project Read Post »

Elevator Installation work

Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals

Date:               xxx Ref:                 CC/269/LW/13 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals Dear Mayur, With ref. to

Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals Read Post »

Elevator installation

Reply to your letter ref. no: NI16-026-SCH-CAB-004, dt.xxx

Date:               xxx Ref:                 CC/269/LW/12 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Reply to your letter ref. no:  NI16-026-SCH-CAB-004, dt.xxx Dear Mayur, With ref. to above, after continuous follow up for the shop

Reply to your letter ref. no: NI16-026-SCH-CAB-004, dt.xxx Read Post »

dumb waiter

Regarding dumb waiter drawing rejection by our consultant and its details

Date:               xxx Ref:                 CC/269/LW/11 To:                   Schindler Lift Pars Intl. Ltd Kind Attn:      Mayur Hingorani Project:           2B + G + 14 + Lower Roof Hotel Building Plot No.:          373-1297 at Barsha, Dubai Subject:          Regarding dumb waiter drawing rejection by our consultant and its details Dear Mayur, With ref. to above, the general arrangement drawing