Nomination of the Kitchen Subcontractor and DEWA drawing issue

Nomination of the Kitchen Subcontractor and DEWA drawing issue

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject:                Nomination of the Kitchen Subcontractor nd DEWA drawing issue

Dear sir

With reference  to above, we would like to inform you that the kitchen area work is completely under hold and following issue being highlighted  to confirm that our work under hold, kindly address the filling to employer :

  1. Kicthen Subcontractor has not been Nominated tiill date and MEP letter

Ref 4024/CEMC/2017 dated 02.04.2017 attached herewith is self explanatory regarding their requirement of the Electrical Load of Kitchen equipment fro DEWA submission.

  • Regarding the tiles which were ordered for additional work due to change in drawing, the supplier ordered the tile along with other Citymax  project , we are waiting delivery as well as  amount to be paid  by client our ref to Arkiplan  Ref. Letter.No.CC/AP/356/17; and mail to client dated 02.04.2017.
  • The tile will be  start and be fixed after clearance by kitchen sub con  for MEP work  as per their shop drawing 
  • The variation submitted not approved till date.

This is for your kind information and to do needful and contractor will not be responsible for delay of the project since delay being added and intimation for further claim  for delay of the project .

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *