Quotation for the de moisture mirror from approved mirror supplier

Quotation for the de moisture mirror from approved mirror supplier

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject:               Quotation for the de moisture mirror from approved mirror supplier and        comparison with other suppliers.

Dear Sir,

With reference to the above, we have requested many times to the employer to finalize  and provide supply and fixing the heating pad mirror and to avoid further delay in the partition work  and finally we are submitting the 3 supplier’s Quotation along with other additional work with the intimation that partition work in toilet and toilet tiling can’t be started without fixing the Electrical supply and finalizing the variation work.

Further more, we are attaching the comparison sheet from approved supplier as well as other supplier as mentioned below to select and finalise our variation amount. As we recommend our approved supplier for the mirror wide Ref: CC/AP/269/MAT/CIV/137 dtd. 22.11.2016, is the longest one.  And find the other detail of the variation with positive and negative statement.

AThe new scope of cost analysis from   
1The lowest Supplier AL SABI GLASS AND MIRROR LLCAED 127,200.00
2Cost of the electrical work per point 120 nos @ AED150/POINT will beAED 18,000.00
3Total cost for the mirror and the MEPAED145,200
 Add main contractor 10% of 145,200.00AED 14,520.00
 Total variation cost by adding 1+2+3AED 159,720.00
BThe original scope from BOQ Page BILL NO 11, Page ref. no 11/2/6  (AED126,800.00)  
 Net variation from Item A-B      159,720 – 126,800 =    AED32,920.00 (Thirty two thousand nine hundred  twenty Dirhams Only)  

So, this is for your kind information and request that we can’t close the toilet wall at washbasin area without fixing the electrical conduit and we also need the confirmation of the variation to order the mirror for mock up room also.

Kindly do needful to avoid any delay to execute MEP work and to place the order the mirror for the mock up room.

List of Ataachments:

1. Approved mirror supplier from ARKIPLAN, ref : CC/AP/269/MAT/CIV/137

2. Quotation from AL SABI GLASS & MIRRORS.

3. AL ABBAR ARCHITECTURAL GLASS supplier Quotation (pre qualified supplier)

4. Contract BOQ Page

5. Appendix from volume 2, List of pre qualified supplier for mirror Item 2.7

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager