Mock-up room critical issue
Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Mock-up room critical issue
Dear Sir,
With reference to above, we would like to inform you the following mock-up room critical issues:
ISSUES | COMMUNICATION REFERENCE | ACTION TAKEN BY | REMARKS |
1.) Again yesterday the meeting held on 29.05.17 for the lighting circuit for mock- up room at 10 to 12nn/ issue unsolved. Mr. Sanjoy of Arkiplan will provide final conclusion formally. | CC/AP/426/17 dtd.25.05.17 | Arkiplan | Still depending and multiple alternative/ inspection till 29.05.17 |
2.) Tile corner for ledge wall was not approved till date, we are waiting for your final decision as toilet fully under hold till then. As per instruction on 29.05.17, we called Duplex and waiting for the location address to send the tile sample and rest of the formalities will be by the client’s concerns. | CC/AP/425/17 dtd.23.05.17 | Client/ Arkiplan | Mock-room toilet tile and other features are pending |
3.) The communication for Home Centre with ref. CC/HC/005 dtd. 17.05.17 is still waiting for their reply. Shall we proceed to close the wall as we received the Media Hub boxes at site with our intimation letter. (decision awaited) | CC/AP/430/17 dtd. 29.05.17 | Client/ Arkiplan | The client/consultant need to involve for DLP and other issue raised by them |
4.) We are waiting the final RCP drawing with details to submit our variation. | CC/AP/424/17 dtd.23.05.17 | Client/Arkiplan | Impact in MEP submission and variation |
5.) The client’s approval of window sill samples for mock-up room | CC/AP/427/17 dtd. 25.05.17 | Client/ Arkiplan | Mock-up room issue. |
This is for your kind information and needs necessary actions.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager
Md Abu Zaed Khan