Author name: Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Reply - Notice of Delay

Running Invoice certification issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:                 Regarding Running Invoice certification issue. Dear Sir, With reference to the above, the meeting held in xxx in the month of January, it was agreed by […]

Running Invoice certification issue Read Post »

False ceiling work

Regarding partition work drawing approval, variation issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:                Regarding partition work drawing approval, variation issue and                            subcontractor letter Ref: CTI/CMC/Dubai/2017                              Dear Sir, With reference to the above, we have raised this issue many

Regarding partition work drawing approval, variation issue Read Post »

DE moisture mirror

Quotation for the de moisture mirror from approved mirror supplier

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:               Quotation for the de moisture mirror from approved mirror supplier and        comparison with other suppliers. Dear Sir, With reference to the above, we have requested many

Quotation for the de moisture mirror from approved mirror supplier Read Post »

Kitchen Equipment

Nomination of the Kitchen Subcontractor and DEWA drawing issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:                Nomination of the Kitchen Subcontractor nd DEWA drawing issue Dear sir With reference  to above, we would like to inform you that the kitchen area work

Nomination of the Kitchen Subcontractor and DEWA drawing issue Read Post »

structural-shop-drawing

Regarding the revised partition drawing, your comment

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:                 Regarding the revised partition drawing, your comment                             “Not approved” and our concerns regarding the same Dear Sir, With reference to the above, we would like

Regarding the revised partition drawing, your comment Read Post »

dry wall partition works

issue of the partition wall work including mock up room

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:            Regarding the issue of the partition wall work including mock up room for GRMS                   subcontractor nomination and follow up. Dear Sir, With reference to the above,

issue of the partition wall work including mock up room Read Post »

office-checks

Project status update for discussion

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:            Status up date for discussion help on 29.03.17 at site. Dear Sir, With reference to the above, we would like to inform you that on 29th

Project status update for discussion Read Post »

Tower Crane

Your Instruction for Tower Crane and our reply

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Your Instruction for Tower Crane and our reply Dear Sir, With reference to above, as we extended the tower crane by adding 3 members with minor

Your Instruction for Tower Crane and our reply Read Post »

Slow Progress

Slow progress of work- External Plaster

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Reply to your letter Ref: xxx reegaring slow progress of work- External Plaster Dear Sir, With reference to the above, we would like to inform you

Slow progress of work- External Plaster Read Post »

Chiller

Chiller delivery and the payment from the supplier

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Intimation of the Chiller delivery and the payment from the supplier and release the payment. Dear Sir, With reference to the above, the expected delivery of

Chiller delivery and the payment from the supplier Read Post »

Scroll to Top