Delay in the certification of our invoice

Taking over Service Lift and Submission of Third-Party Certificate

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         : Taking over Service Lift and Submission of Third-Party Certificate for your record

Dear Sir,

Kindly find attached copy of inspection certificate issued by Elite Safety Consultants for the service lift, as a proof for the safety of the usage of service lift which is being handover by Schindler to the main contractor with rental cost under their maintenance and responsibility.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager