Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha
1st, Dubai U.A.E.
Subject: Delay in casting the 10the floor slab
Dear Sir,
With reference to above, we would like to inform you that we have started the concreting for 10th slab and Neighbors have complained to Dubai municipality for noise during casting of concrete by placing boom in night time (after 9p.m).
So , We Stopped the process of casting the concrete and DM instructed not to disturb the neighbor’s in night time and Yesterday was Friday i.e., 20.01.17, plant did not operated due to regular maintenance.
So, We have planned to cast today in day time due to stoppage by authority.
This is for your kind information that our casting of slab no. 10 is delayed due to external instruction by local authority .
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager