Painting works

Regarding not execute any work without approval of the material approval and method of statement and sample board

Date: xxx                  

Ref. xxx

To                  :  M/s. xxx Paint Emirates LTD/ M/s. xxx Technical Service LLC

Kind Att        :  Mr. xxx Kumar

Project         :  2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at

                        Al   Barsha 1st, Dubai, U.A.E.

   Subject      : Regarding not execute any work without approval of the material approval and method of statement and sample board.

 Dear Sir,

We are hereby informing you that consultant letter ref no: AP/26/CC/413 dtd 26th August 2017 is self-explanatory that without approval of the material approval and samples as well as method of statement you are not allowed to execute the work because the consultant held responsible for all contractual obligation

Furthermore also provide Performa of your guaranty/ warranty certificate along with other documents.

Meantime you started the work without helding the safety induction and training which is mandatory for Dubai Municipality and we must have the copy of agreement at site as a proof which required during the investigation by DM for any incident /unforeseen event.

So, kindly follow the instruction and do the needful.

Thanking you,

For xxx Contracting L.L.C

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top