Date: xxx
Ref no:CC/HC/004
To :M/s xxx Center
Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai
Subject : Regarding our query to M/s Gypsemna to fix the plywood support inside the partition wall and their reply
Dear Sir,
With reference to the above, we requested M/s Gypsemna to review the ID drawing through our vide letter ref no: GYPSEMNA/CC/ 002 DT.18.03.17 and we are hereby informing the following:
- Item no.1 to 4 are self-explanatory as they specify the special instruction that HHD-S Cavity anchor supplied by M/s Hilti and loading is confirmed already and same has been confirmed at the site meeting in presence of client and consultant.
- In Item no.5, M/s Gypsemna stated that ,the timber within our system will have a detrimental impact on the stated sound insulation .
So, there is no need to fix the plywood. We are intimating to submit your drawing without any plywood support inside the partition and fix the fit out features with HHD-S cavity anchor which must be mentioned and to be used after approval of the sample from specified supplier.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager