Submission of current invoice and to claim of  material at site

Submission of current invoice and to claim of material at site

material delivery

Date: xxx                  

Ref. xxx

To                  :  M/s. xxx Communication DMCC

Project         :  2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at

                        Al   Barsha 1st, Dubai, U.A.E.

Client         :   Mr. xxx

Subject      : Regarding your submission of current invoice and to claim of       

                      material delivery

Dear Sir,

With reference to above we are hereby inform you that we need your invoice for month of February for the work done and against material by considering the following

1)  The claim of the work done at site as per BOQ rate

2) claim of the material delivery, you will get 70% of the actual cost of the material delivery (cost of the material delivered)

3) Any claim against the material deliver you must have the inspection report instructed by the consultant as per you D.O and supporting document for specification / approval with invoice submitted

So kindly note that the invoice to be prepared by considering 1,2,3 and material inspection is mandatory including inspection of the work done

Try to submit the invoice by considering all to avoid any rejection of the invoice

Thanks and regards,

For xxx Contracting L.L.C

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *