Rejection of your claim by main contractor your letter Ref xxx dated xxx

Rejection of your claim by main contractor your letter Ref xxx dated xxx

Date                : xxx

Ref                   : xxx

To                    : M/s. xxx GROUP, PO Box xxx, Sharjah UAE.

Project             : 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject        : Rejection of your claim by main contractor your letter Ref xxx dated xxx and revert back

Dear Mr. Dhruv Singh,

With reference to above we are rejecting your claim for overhead and supervision cost-month Nov 2017 claimed by you based on following fact as described below:

1) You are the nominated sub-contractor and there is no such clause in our contract by which validate your claim and to be analyze

2)You have multiple location for work and nomination for stag bar, all day dining at first floor and additional variation for pelmet including another variation doors of back of house. So, to plan and engage your work with resources smoothing is Destec responsibility and your claim did not specify the particulars  

3) Your work cannot be consider the isolated activity so it was being coordinated with other sub-contractor which have been nominated by client such that kitchen sub-contractor, Aluminium etc for the same area/location

4) CC carried out variation work in your area which is not part of the original scope and that was delayed due to non-availability of the MEP drawings and complete coordination from you and other sub-contractor and required additional time

5) The ceiling work was also hold because of the non- nomination of the lighting control sub-contractor and our MEP coordination effected due to the same

6) Many technical queries under consideration for ID consultant like column cladding, floor mounted socket and work related at bar counter which are still going on

7) The requirement of the third party consultant inspection for fire protection system at project area is instructed by client very recently in last week of Feb 2018 and because of that we are redoing the work at the project including your area also as stated by client as it is mandatory now by DCD

So, the main contractor did not hold your work and we are reverting back your claim and for your record

This is for your kind information.

Regards,
For xxx Contracting L.L.C                        

xxx                                       

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *