Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha
1st, Dubai U.A.E.
Subject : Intimating that Progress of slab no.12 is stopped due to Full day rain on dated xxx
Dear Sir,
With reference to the above, Our progress of the slab no.12 is badly affected due to rain which is the force measure/act of God and this not under control of the contractor
Related posts:
To Release the Id Drawing from 3rd Floor as Well as Comments in the Tile Corner by Id
Second Floor Sunken Area Piping and Intimation for Filling.
So, slab no.12 being continuously affected because rain is happening in irregular interval and unfortunately today it is raining since morning.
This is for your kind information that we cannot work or operate electrical equipment or any tools to avoid any risk or hazardous condition.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager