Minutes of meeting held between Main contractor, pool subcontractor and client representative

Minutes of meeting held between Main contractor, pool subcontractor and client representative

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding Minutes of meeting held between Main contractor, pool subcontractor and client representative Mr.xxx

Dear Sir,

With reference to above, as per the meeting discussion held between Main contractor, pool subcontractor and client representative Mr.xxx, We are updating the discussion below:

SL NOMEETING DISCUSION /DESCRIPTIONACTION TAKEN  BY
1Main Contractor provided the commented shop drawings to the pool subcontractors to comply and return the sameM/s United Technology
2Main contractor provided the structural and architectural drawings for the beams with formal discussionM/s United Technology
3Main contractor provided architectural, structural and ID soft copy of drawingsM/s United Technology
4Main contractors has informed that it is very difficult to construct the RCC tank because of many cross beams and pipeline maintenance in future due to confined space .GRP tank is most advisable and to accommodate in mechanical room located below the poolM/s United Technology
5Main contractor has intimated pool subcontractor that sleeves to be designed in all the beams due to the depth of the beam concernM/s United Technology
6Main contractor has intimated the pool subcontractor for the heat and pool pump that should not be placed in front of the staircase exit door and we have supported the location for cross checkM/s United Technology
7Main contractor has intimated pool subcontractor to provide signed approved quotation copy.    M/s United Technology
8Client representative Mr.John have intimated to pool subcontractor to provide the drawings at the earliest on Tuesday.M/s United Technology
9Main contractor will coordinate the pool subcontractor, the mechanical floor layout to find the option for circular GRP tank.(link provided)  M/s United Technology
10Contact numbers  of concerned person named Mr.Ramlal (Project manager) and Mr. Rakesh(Mep Engineer) are given and requested for organization chart by the Main contractor for any further assistanceM/s United Technology
11Main contractors intimated that all the information communicated through Main contractors only.  M/s United Technology

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager