METHOD STATEMENT FOR WIRES AND CABLES INSTALLATION

Method Statement Title: Testing of Lv Cables / Wires

Method Statement Title: Testing of LV Cables / Wires

1.0       Scope

  1. Testing of LV Cables / Wires installed in Tower according to the requirement of the Project Specification.

2.0       Material

  • XLPE / SWA / PVC cables,
  • PVC Insulated Cables and Flexible wires.

3.0       Testing Equipment

  • Continuity Tester
  • Insulation resistance tester. (Megger)

Note : The Calibration certificates of testing instruments shall be verified to have current certificate, prior to usage.

Related posts:
Method Statement Title: Testing and Commissioning of Emergency Lighting System
Method Statement Title: Testing of Lightning Protection System

4.0       Testing and Commissioning Method

4.1       Physical Checks

  • Physical checks will be conducted as follow, prior to testing:
  • Check the cables are layed properly with proper and adequate support arrangement (i.e. supported in cable trays, trunking, ladder etc.) properly layed, dressed and cleated/tied with cable cleats/ties.
  • Check the cable support arrangements are fixed to the building structure rigidly.
  • Check the Identifications and labeling are provided according to the specification and DEWA requirement.
  • Check the glanding and gland earthing termination is correct.
  • Check if there are any physical damages. Replace as required if any major damages are noticed.

4.2       Insulation Resistance Test

  • Insulation resistance test will be done by applying 0.5kV for the below mentioned points with suitable insulation resistance tester (Megger).
  • Phase to Phase.
  • Phase to Neutral.
  • Phases to Earth.
  • Record all results and details as per attached format. The readings to be verified with permissible limits.
  • Phase rotation test shall be conducted after energisation.
  • Check if there is any over heating of cables after a 2 hours of energisation.
  • Suitable corrective action shall be taken if any discrepancies are found.
  • Inspection requests shall be raised for consultant to witness the testing (random test).

5.0       Records

5.1       Inspection request duly signed-off by NMX and Consultant.

  • Attachment
  • Cable continuity and Insulation test report .