Risk Assessment for Emergency Lighting system

Method Statement Title: Testing and Commissioning of

Method Statement Title: Testing and Commissioning of Emergency Lighting System

Related posts:
Method Statement Title: Testing of Lightning Protection System
Method Statement Title: Testing of Earthing System

1.0       Scope

This method statement details the Testing and Commissioning of Emergency Lighting System, as per Project Specification 16536

            Note

            A separate Method Statement Ref. ETA/MS/E- 014 shall be submitted for Installation of  the Emergency Lighting System.

2.0       Material

  • All materials shall be as per approved material submittals
  • Sizes of FP200 cable shall be as per approved shop drawings / system manufacturers recommendation.

2.3       Type of emergency / exit luminaire shall be as per approved shop drawings.

            2.4       Direction sign of Exit luminaries shall be as per approved shop drawings.

3.0       Applicable Location

            3.1       Tower E1, E2, E3, W1, W2, W3  and Podium Areas.

4.0       Method

Find attached the manufacturer representative’s detailed method statement and test formats for testing and commissioning of Emergency Lighting system covering the mechanical checks, insulation resistance measurement, switching ON the unit. Programming and testing

The whole system will be commissioned and certified by the manufacturer’s representative before handing over.

5.0       Safety

5.1       Safety Officer shall ensure that the technicians have undergone safety induction programme.

            5.2       Only experienced technicians shall be engaged for this specialized job.

5.3       Workmen shall be given proper training to use PPE and to be monitored to avoid any violation on the same. 

5.4       Electric tools to be checked and certified by Safety Officer and earthing of the same shall be ensured.

5.5       All other safety precautions shall be followed as per established safety plan and procedures.

6.0       Records

            6.1       Commissioning procedure with test results in attached format.

            6.2       Inspection request duly signed-off by NMX and Consultant.

            6.3       Certification of installation by  CEAG.

  • Attachment

7.1       Manufacturer’s representative method statement detailing the pre-commissioning and commissioning procedures, including test formats