METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

Method Statement Title: Installation of Low Voltage Panels

Method Statement Title: Installation of Low Voltage Panels (LVP’s). – 1.0       Scope

Method Statement Title: Installation of Low Voltage Panels (LVP’s).

  1. This method statement details the method of installation of L.V main Panels (LVPs) according to the Specification Section 16402.

Note : A separate Method Statement ref. ETA/MS/E-29 shall be submitted for Testing & Commissioning.

2.0       Material

  • All materials shall be as per approved material submittals, shop drawing and single line diagram.
    • L.V. Main Panels.
    • Cable glands and lugs.
    • Identification labels and tags.

3.0       Applicable Location

  • L.V. rooms for E1,E2,E3 & W1,W2,W3 Towers Located in Podium areas.

4.0       Method

  • Storage  

Note: L.V. Panels will be offered for factory inspection/witness by Design Consultant prior to material dispatch

  • LVP’s shall be inspected upon receipt at site for damages and compliance with the approved submittals and Single line Diagram.
  • Upon completion of receiving inspection, the LVP’s shall be positioned at the respective substation locations with suitable crane arrangements.
  • LVPs found with transportation damages shall be recorded and notified to the concern party for further action.
  • LVP’s shall be covered with polythene sheets to protect from dust and moisture.

4.2       Installation

  • Ensure approved documents like shop drawing, SLD, electrical room layout and load schedules are available with the installation team.
  • Check the label/marking to ensure that it is the right panel and check the position according to the shop drawing.
  • Check the breaker rating and the provision for cable / bus bar termination.
  • Set the breaker current rating as per approved shop drawing.
  • Terminate the incoming and outgoing cable as per single line diagram using proper tools.
  • Megger the panels after connecting the compartments.
  • Megger the cables before terminating.
  • Megger the panel after termination, when I/C open and O/G closed.
  • Check working of motorized breakers.
  • Clean the termination and breaker cubicles with vacuum cleaner and hand brush to clean the dust and small metal pieces fallen during cable cutting and terminating process.
  • Ensure the busbars and interconnecting terminals are free from dust and damage.
  • Provide identification for all the cable termination as per specification requirement and SLD.
  • Dress the cables neatly with cable ties / cable cleat.
  • Double check the connections by tightening the terminations.
  • Keep the approved single line diagram near the LVP’s (photo framed), wall mounted inside the substation.
  • Inspection shall be offered for QC Verification before DEWA inspection.

6.0       Records

            6.1       QC Inspection Check List.

  • Inspection request duly signed-off by NMX and Consultant.

7.0       Attachment

  • Inspection Check List for L.V. Panels .

EngineersBlog Home | Method Statement Title: Installation of Low Voltage Panels (lvp’s). – Method Statement Title: Installation of Low Voltage Panels (LVP’s).

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Installation of Low Voltage Panels (lvp’s). – Method Statement Title: Installation of Low Voltage Panels (LVP’s).”, “description”: “This method statement details the method of installation of L.V main Panels (LVPs) according to the Specification Section 16402”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T11:49:03+04:00”, “dateModified”: “2022-11-06T11:49:31+04:00”, “url”: “https://engineersblog.net/method-statement-title-installation-of-low-voltage-panels-lvps/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Installation of Low Voltage Panels (lvp’s). – Method Statement Title: Installation of Low Voltage Panels (LVP’s).”, “item”: “https://engineersblog.net/method-statement-title-installation-of-low-voltage-panels-lvps/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top