Method Statement Title: Installation of Generator and Ats.

Method Statement Title: Installation of Generator and ATS. – 1.0       Scope

Method Statement Title: Installation of Generator and ATS.

  1. This method statement details the method of installation of Generator and ATS according to the Specification Section 16402.

Note : A separate Method Statement Ref. : ETA/MS/E-039 shall be submitted for Testing & Commissioning of Generator and ATS.

2.0       Material

  • All materials shall be as per approved material submittals, shop drawing and single line diagram.
    • Generator & ATS.
    • Cable glands and lugs.
    • Identification labels and tags.

3.0       Applicable Location

  • Generator: East & West Podium – Ground floor.
  • ATS: Tower E1, E2, E3 & W1, W2, W3 – LV Rooms.

4.0       Method

  • Storage  
  • Generator & ATS shall be inspected upon receipt at site for damages and compliance with the approved schematic.
  • Upon completion of receiving inspection, the Generator & ATS shall be positioned at the correct locations with suitable crane arrangements.
  • Generator & ATS found with transportation damages shall be recorded and notified to the concern party for further action.
  • Generator & ATS shall be covered with polythene sheets to protect from dust and moisture.
  • Installation
  • Generator:

4.2.1.1 Installation Procedure:

  • Specification sheets will be checked for the dimension & weight of the generator sets and mounting points.
  • DG set of both ratings will be mounted on a concrete plinth.
  • Installation locations will be as per approved shop drawings.
  • Engine Exhaust System:
  • Flexible exhaust tubing will be connected to the engine to take up thermal expansion and generator set movement and vibration.
  • Exhaust silencer shall be mounted so that the engine does not support the weight of the silencer.
  • Flexible tubing will not be used to form bends or to compensate for misalignment of piping.
  • Mufflers and piping will be supported by Non-combustible hangers or supports.
  • Precaution shall be taken to rule out any possibility of combustible material coming in contact, close to the exhaust piping. Approved non-combustible material shall be used where exhaust piping pases through combustible walls or ceiling etc.
  • Horizontal runs of exhaust piping will be sloped downwards away from the engine to out of doors to avoid condensate water entering engine.
  • Installation will be as per approved shop drawings.
  • Exhaust pipe opening outside the building shall be arranged to avoid entry of rainwater and shall be fitted with bird guard.
  • On confirmation of the routing of the exhaust pipe, the number of bends & length will be communicated to the manufacturers & suitable diameter of exhaust pipe will be selected for minimum back pressure.
  • Air Intake and Radiator Exhaust
  • Intake and exhaust air louvers will be sized and located to provide sufficient intake air for engine combustion and to provide required airflow through the radiator.
  • Duct work with flexible connecting section will be sized and located to provide sufficient intake air for engine combustion and to provide required airflow through the radiator.
  • The allowable pressure drop will be checked with the manufacturer after confirming the layout and will informed to the louver supplier / manufacturer, for co-ordination purposes.
  • Access for Installation
  • Access opening for installing the Generator will be indicated on shop drawings.

4.2.2    ATS :

  • Ensure approved documents like shop drawing, electrical room layout are available with the installation team.
  • Check the label/marking to ensure that it is the right panel and check the position according to the shop drawing.
  • Terminate the incoming and outgoing cable as per single line diagram using proper tools.
  • Megger the panels after connecting the compartments.
  • Megger the cables before terminating.
  • Megger the panel after termination.
  • Clean the termination and ATS panel with vacuum cleaner and hand brush to clean the dust and small metal pieces fallen during cable cutting and terminating process.
  • Provide identification for all the cable termination as per specification requirement.
  • Dress the cables neatly with cable ties / cable cleat.
  • Double check the connections by tightening the terminations.
  • Inspection shall be offered for QC Verification.

5.0       Records

  • QC Inspection Check List.
    • Inspection request duly signed-off by NMX and Consultant.
  • Attachment

6.1       Inspection Check List for Generator & ATS.

EngineersBlog Home | Method Statement Title: Installation of Generator and Ats. – Method Statement Title: Installation of Generator and ATS.

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Installation of Generator and Ats. – Method Statement Title: Installation of Generator and ATS.”, “description”: “This method statement details the method of installation of Generator and ATS according to the Specification Section 16402.”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T11:47:27+04:00”, “dateModified”: “2022-11-06T11:47:58+04:00”, “url”: “https://engineersblog.net/method-statement-title-installation-of-generator-and-ats/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Installation of Generator and Ats. – Method Statement Title: Installation of Generator and ATS.”, “item”: “https://engineersblog.net/method-statement-title-installation-of-generator-and-ats/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top