METHOD STATEMENT FOR AHU INSTALLATION

Method Statement Title: Installation of Fresh Air Handling

Method Statement Title: Installation of Fresh Air Handling Units (Floor Mounted)

Method Statement Title: Installation of Fresh Air Handling Units (Floor Mounted)

1.0       Scope

  1. This method statement applies to the installation of floor mounted air handling units as per the Specification Section 15700.
  • Purpose
  • Purpose of this method statement is to outline the method of storage and installation of Floor mounted Air Handling Units.
  • Material
  • Fresh air handling units.
  • Pipes and fittings as per approved submittals/drawings.
  • Ducting and accessories as per approved submittals/drawings.
  • Electrical cables, control panel, other accessories if any, as per approved drawings and submittal.
  • Method
  • Receiving
  • On arrival at site all Air Handling Units (AHUs) shall be checked for quantities, type and model number, physical damages, orientation of coil connections, access doors, etc.
  • Upon delivery material on site inspection shall be carried by R&P/NMX/MACE.
  • Upon satisfactory inspection the AHUs shall be stored properly with protective covering.
  • Preparation
  • Check the AHUs foundation and ensure it is as per approved drawings.
  • Check the area around the foundation and ensure access to the AHUs from all sides as applicable.
  • Ensure availability of sufficient slope to the drainpipe, for easy draining of condensate drain.
  • Check the foundation surface and it shall be smooth finish to avoid any dust accumulation.
  • The foundation surface shall be even in all directions.
  • The foundation surface shall be cleaned before installation of AHUs.
  • Mark the AHUs position on the foundation for centralisation.
  • Place the anti vibration ribbed rubber pads of correct thickness as per approved drawings/submittals.
  • In case of multiple rubber pads the pads shall be placed one above the other, with the ribs at right angle to each other.
  • AHU sections are assembled at site/location by factory trained personal.
  • Installation
  • Shift the AHUs to the place of installation in safe manner using fork lift/crane as applicable. Sufficient manpower will be engaged as required for safe shifting and installation.
  • Ensure that the correct AHU is shifted to the place of installation.
  • Air inlet, outlet, fresh air connection and chilled water connection orientation are as per approved drawings.
  • If the AHUs are shipped in multiple sections, the AHUs will be assembled strictly as per the manufacturer’s instructions.
  • Remove the movement arrestors provided inside AHUs at Fan and impeller which are fixed during transportation.
  • The AHUs are placed correctly on foundation with vibration isolator rubber pads at right location.
  • The AHUs will be properly levelled and parallel to room walls/other installations.
  • AHUs shall be inspected again for any damage during hoisting/shifting and installation by R&P/ETA.
  • Upon satisfactory positioning of AHUs any open air/water outlets of AHUs shall be closed properly and area shall be cleaned, complete protection in areas where other trades are working.
  • Air, Chilled water, Electrical and Condensate Drain connections
  • Air side connections
  • Ducting connection shall be done as per approved shop drawings.
  • Provide flexible duct connections as applicable/as approved submittal.
  • Provide proper supports as per approved drawings.
  • The weight of ducting shall not act on AHUs panel.
  • Before making final connections to AHUs ensure inner area of AHUs is clean, especially the impeller of the fan.
  • Chilled Water connections
  • Chilled water connections shall be made as per approved drawings.
  • Ensure supply and return connection is made properly.
  • Provide pipe flexible connection and other piping accessories as per approved drawings and submittals.
  • The piping shall be free of any strain and shall not exert any load on, AHUs panel/AHUs.
  • Provide vibration isolators to piping supports as per approved submittals/drawings.
  • Install the control valves, strainer, commissioning set correctly as per direction of flow as per approved drawings.
  • Ensure proper operation of valve handles and sufficient space for valve installation.
  • The location and orientation of the gauges and commissioning sets shall allow for easy accessibility and readability of readings.
  • Electrical connections
  • Electrical power connections shall be done as per approved drawings.
  • Cables shall be installed and terminated as per approved method statement Ref;ETA/MS/E/015.
  • Condensate drain piping connections
  • Condensate drain piping shall be terminated at the nearest floor drain.
  • Provide the `U’ trap in the condensate drain piping.
  • Ensure provision for cleaning of `U’ traps.
  • Ensure proper slope to enable easy draining.
  • Ensure trap is deeper than ESP of  fan – eg., 70mm > 650pa
  • Cleaning
  • Clean the interiors of AHUs including the impeller, drain tray.
  • After completion of installation, it shall be checked and certified by the supplier/manufacturer and inspected by R&P/ETA.

4.6       Testing

  • The piping connections to AHUs shall be pressure tested to 1.5 times the working pressures. Coils not included in test.
  • Strainer shall be cleaned after pressure testing and initial flushing of chilled water piping system.
  • Flow test of the AHUs drain tray, condensate drain pipe and ensure water is drained out completely.
  • Inspection
  • Work Inspection Request (WIR) shall be raised for consultant’s inspection.
  • QC inspection shall be carried out as per the installation checklist and manufacturer’s instructions.
  • Inspection shall be recorded in the approved format and signed off by R&P.
  • Safety
  • All safety precautions shall be followed as per established project safety plan and procedure.
  • Only experienced and skilled technicians shall be engaged for carrying out AHUs installation work.
  • The people involved in the installation shall use PPE such as safety helmets, safety shoes, harnesses, gloves, etc as required.
  • Safety officer shall check and ensure that all safety precautions are followed.
  • Safety officer shall check and ensure that all scaffolding and ladders used at site are having duly signed tags.
  • Reference
  • Manufacturers catalogue.
  • Approved submittal.
  • Shop drawings.
  • Specification section 15700.
  • Records
  • `Work Inspection Request’ (WIR) duly signed by the Consultants.

8.2       Air Handling Unit installation checklist signed off by R&P.

EngineersBlog Home | Method Statement Title: Installation of Fresh Air Handling Units (floor Mounted) – Method Statement Title: Installation of Fresh Air Handling Units (Floor Mounted)

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Installation of Fresh Air Handling Units (floor Mounted) – Method Statement Title: Installation of Fresh Air Handling Units (Floor Mounted)”, “description”: “Shift the AHUs to the place of installation in safe manner using fork lift/crane as applicable. Sufficient manpower will be engaged as”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T21:17:19+04:00”, “dateModified”: “2022-11-06T21:17:57+04:00”, “url”: “https://engineersblog.net/method-statement-title-installation-of-fresh-air-handling-units-floor-mounted/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Installation of Fresh Air Handling Units (floor Mounted) – Method Statement Title: Installation of Fresh Air Handling Units (Floor Mounted)”, “item”: “https://engineersblog.net/method-statement-title-installation-of-fresh-air-handling-units-floor-mounted/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top