Method Statement Title: Installation of Fans (central Exhaust)

Method Statement Title: Installation of Fans (Central Exhaust)

Method Statement Title: Installation of Fans (Central Exhaust)

Scope

  1. This method statement applies to the installation of Central Exhaust Fans as per the Specification Section 15800.
  • Purpose
  • Purpose of this method statement is to outline the method of storage and installation of Central Exhaust Fans.
  • Material
  • Exhaust fans.
  • Ducting and accessories as per approved submittals/drawings.
  • Electrical cables, control panel & other accessories if any, as per approved drawings.
  • Method
  • Receiving
  • On arrival at site all Fans shall be checked for quantities, type and model number, physical damages, etc., and notify supplier of any discrepancies.
  • Upon satisfactory inspection, the fans shall be stored properly with protective covering.
  • Any items found damaged or not suitable as per the project requirements shall be removed from site. Until such time, the damaged/non-compliant material shall be clearly marked and stored separately to prevent any inadvertent use.
  • Preparation
  • Check and ensure all drawings used for installation are latest and approved for construction.
  • For Floor Mounted Fans
  • Check the fan’s foundation and ensure it is as per approved drawings.
  • Check the area around the foundation and ensure access to the fans from all sides as applicable.
  • Check the foundation surface and it shall be smooth and even finish to avoid any dust accumulation.
  • The foundation surface shall be cleaned before installation of fans.
  • Mark the fan’s position on the foundation.
  • Fix the anti-vibration mounts/pads as applicable as per approved drawings/submittals.
  • For Ceiling Suspended Fans
  • Check and ensure that clearance and proper access is available at the place of installation.
  • Mark the support locations as per approved drawings/manufacturers details and fix the approved anchor fasteners in the slab.
  • Fix the hanger rods and supports as per manufacturers instructions.
  • Provide anti vibration isolators as applicable as per the approvals.
  • Ensure easy access and sufficient clearance for maintenance and removal of fan/motor.
  • Installation
  • Floor Mounted Fans
  • Shift the fans to the place of installation in safe manner using hand trolley, fork lift/crane as applicable. Sufficient manpower will be engaged as required for safe shifting and installation.
  • Ensure that the correct fan is shifted to the place of installation.
  • Ensure air inlet and outlet connections orientation are as per approved drawings.
  • Fix the flexible duct connector to fan inlet and outlet as per approved drawings/manufacturers instructions.
  • The fan is placed correctly on foundation with anti vibration mounts (if applicable) at the right location.
  • The fans will be properly levelled and parallel to room walls/other installations.
  • Fans shall be inspected again for any damage during hoisting/shifting and installation.
  • Clean the interior of the fans.
  • Follow the manufacturer’s instructions while installing the fans.
  • For Ceiling Suspended Fans
  • Shift the fans to the place of installation in safe manner using hand trolley, fork lift/crane as applicable. Sufficient manpower will be engaged as required for safe shifting and installation.
  • Ensure that the correct fan is shifted to the place of installation.
  • Ensure air inlet and outlet connections orientation are as per approved drawings.
  • Fix the flexible duct connector to fan inlet and outlet as per approved drawings/manufacturers instructions.
  • Lift and install the fan carefully on the supports. Engage sufficient manpower as required for safe installation.
  • Check the level of the installation in co-ordination with other services and approved drawings.
  • Cut and trim the support rods after finalising the levels. Leave 25mm extra length of support rods for final adjustments. Threaded rod ends to be painted zinc rich primer.
  • Remove burrs and sharp edges if any.
  • Fans shall be inspected again for any damage during hoisting/shifting and installation.
  • Clean the interior of the fans.
  • Follow the manufacturer’s instructions while installing the fans.
  • Air side and Electrical Connections
  • Air side connections
  • Ducting connection shall be done as per approved shop drawings.
  • Provide proper supports as per approved drawings.
  • The weight of ducting shall not act on fans.
  • Install the sound attenuators if applicable as per approved drawings and material submittals.
  • Before making final connections to fans ensure inner area of fans is clean, especially the impeller of the fan.
  • Electrical connections
  • Electrical power connections shall be done as per approved drawings.
  • Cables shall be installed and terminated as per approved method statement Ref;ETA/MS/E/015.
  • Inspection
  • Work Inspection request shall be raised for consultant’s inspection and sign off.
  • QC inspection shall be carried out as per the installation checklist and manufacturer’s instructions.
  • Inspection shall be recorded in the approved format.
  • Safety
  • All safety precautions shall be followed as per established project safety plan and procedure.
  • Only experienced and skilled technicians shall be engaged for carrying out fans installation work.
  • The people involved in the installation shall use PPE such as safety helmets, safety shoes, harness, gloves, etc as required.
  • Safety officer shall check and ensure that all safety precautions are followed.
  • Safety officer shall check and ensure that all scaffolding and ladders used at site are having duly signed tags.
  • Reference
  • Manufacturers catalogue.
  • Approved submittal.
  • Approved shop drawings.
  • Specification section 15800.
  • Records
  • `Inspection Request’ duly signed by the Consultants.

8.2       Signified off Fan’s installation checklist.

EngineersBlog Home | Method Statement Title: Installation of Fans (central Exhaust) – Method Statement Title: Installation of Fans (Central Exhaust)

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Installation of Fans (central Exhaust) – Method Statement Title: Installation of Fans (Central Exhaust)”, “description”: “Shift the fans to the place of installation in safe manner using hand trolley, fork lift/crane as applicable. Sufficient manpower will be enga”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T21:15:08+04:00”, “dateModified”: “2022-11-06T21:15:40+04:00”, “url”: “https://engineersblog.net/method-statement-title-installation-of-fans-central-exhaust/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Installation of Fans (central Exhaust) – Method Statement Title: Installation of Fans (Central Exhaust)”, “item”: “https://engineersblog.net/method-statement-title-installation-of-fans-central-exhaust/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top