Purpose of work: It describes the methodology for the execution work for the Ramp Slab Formwork from Starting Point
EXECUTION
- Surveyor has given marking for the proper measurement for the Ramp Level and Length.
- The slope started towards maximum 40 cm. ht. from SSL.
- After casting the slope area from 0.00 level to 40cm ht., we have to start wood formwork/ shutter towards Water Tank Area.
With this, we are assuring that the 40 cm. ht. is enough and accessible to do the de-shuttering/ dis- mantling of formwork .
Note: Kindly see Submittal Ref. No. CC/AP/269/00/126
Submission of Shop Drawing for Ramp Shuttering at Basement 2 ( Formwork)