CHECK LIST FOR INSTALLATION OF EXTERNAL FIRE HYDRANT

Method Statement for Installation,testing & Commis (2022-10)

CONTENTS

  1. 1.0 PURPOSE
  2. 2.0 SCOPE
  3. 3.0 REFERENCES
  4. 4.0 DEFINITIONS
  5. 5.0 RESPONSIBILITIES
  6. 6.0 EQUIPMENTS
  7. 7.0 PROCEDURE
  8. 8.0 ATTACHMENTS

 

 

1.0 PURPOSE

  • This method statement is applicable for the Installation, Testing & Commissioning of External Fire Hydrant for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

  • This method Statement shall cover the Supply, Installation, Testing & Commissioning of External Fire Hydrant in line with project requirements as indicated in the Approved Shop Drawings, specifications & manufacturer’s instructions.

3.0 REFERENCE

      3.1  Latest Approved shop drawings intended for Fire Fighting System

            3.2  Specifications

  • Project Quality Plan
    • Project HSE Plan
    • Material Approval
    • Approved Method Statement for Installation & Testing for Fire Fighting System & Accessories                                                

4.0 DEFINITIONS

  • PQP                             : Project Quality Plan
  • PSP                              : Project Safety Plan
  • QCP                             : Quality Control Procedure
  • HSE                             : Health, Safety and Environment
  • MS                               : Method Statement
  • ITP                               : Inspection Test Plan
  • QA/QC                         : Quality Assurance / Quality Control Engineer.
  • WIR                             : Inspection and Test Request
  • MIR                             : Material Inspection Request
  • UPVC Class E              : Ultra polyvinyl chloride
  • UPVC                          : Ultra polyvinyl chloride
  • HDPE                           : High density polyethylene
  • PEX PIPE                     : Cross-linked Polyethylene
  • G.I. Pipe                       : Galvanized Iron Pipe

5.0 RESPONSIBILITIES:

            5.1 Project Manager

5.2 Construction Manager

5.3 Site Engineer

5.4 QA/QC Engineer (MEP):

5.6 Safety Officer

            5.7 Store Keeper (SK)

6.0  EQUIPMENTS

Following tools shall be arranged before starting the job.

 

7.0   PROCEDURE

 

Ø  Work Sequence/Procedure

  • General Requirements
  •  External Fire Hydrant to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc., should be reported to the supplier for rectification or replacement & to be removed from site immediately.

            7.2        Delivery & Storage

            7.2.1     Material Transport/ Delivery

7.3        Storage

            7.3.1  Storage on Site Store

            7.4 Sequence of Installation for the External Fire Hydrant

7.4.1 Safety

7.4.2 Pre- Installation Procedure

7.4.3.2.2 Installation Procedure of Butterfly Valves:

7.4.4. Testing & Commissioning Procedures

7.4.4.1 Visual Inspection & Testing Procedure

8.0.  ATTACHMENTS

8.1.            Inspection & Test Plan                                   

8.2.            Installation Check Sheet                                          

  • Testing & Commissioning Check Sheet                  

Risk Assessment 