Regarding rejection the inspection held on 19.06.18 and remarks pending to attend by NAFCO as well as handing over key in proper manner - Construction Template

Handing Over the Stag Bar Area to Start the Work at Site

Date                : xxx

Ref                   : xxx

To                    : M/s. xxx GROUP, PO Box xxx, Sharjah UAE.

Project             : 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject         : Handing over the Stag Bar Area to start the work at site.

Dear Mr. Dhruv,

With reference to above, we are hereby handing over the stag bar area on Saturday (23/09/17) onwards and intimating you to start the work and coordination with MEP sub contractor at site.

  1. We hereby acknowledge the receipt of the kitchen drawing at stag bar area and 1st floor and having no objection.
  2. You hereby instructed to coordinate with MEP contractor (Chirag Electro Mechanical) in order to execute your scope of work.

This is for your kind information and Please acknowledge. 

Regards,
For xxx Contracting L.L.C                       

xxx                                       

Project Manager     