Confirmation of Ground Water Table Level

REF: No. xxx

Date: December 18, xxx

xxx ARCHITECTURAL & ENGINEERING CONSULTANCY
Office No. xxx, Sobha Ivory 2, Business Bay

P.O. Box xxx, Dubai, UAE

Project: Residential Villa (G+1) & Pump Room Block, On Plot No. xxx at Al Barari – Dubai, UAE for xxx

Subject: Confirmation of Ground water table level

Dear Sir,

With reference to the above-mentioned subject, kindly find attach confirmation of ground water table level from dewatering subcontractor M/s. xxx Plant for Dewatering & Drainage services LLC. They have mentioned that; actual ground water level is -2.10 m from existing ground level.

This is for your information and record.

Yours Sincerely,           

MCM LLC