To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room)

To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room)

Date: xxx

Ref no: xxx

To             :M/s xxx Center

Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai

Subject       : To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room)

Dear Sir,

With reference to the above, we are here by requesting you we need your clearance that your sliding door work has been complete100% in mock up room unit no -05 and we want to start our false ceiling work.

So, we are hereby intimates you to provide written confirmation as our successor activity will be executed after clearance.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager