Request for permit to place minor road diversion to place concrete pump in front of the plot

Concrete Pump

Ref: xxx Date: xxx To, Right of way Authority Traffic control Section Dubai, UAE Project:             2B+G+14+Lower Roof xxx Hotel Building Plot No. :           xxx Location:           Al Barsha 1st, Dubai, UAE Client:                xxx Consultant:       … Continue reading Request for permit to place minor road diversion to place concrete pump in front of the plot

Regarding renewal of Permit for Building construction or Demolition

Site Meeting

Ref: xxx Date: xxx To, Right of way Authority Traffic control Section Dubai, UAE Project:             2B+G+14+Lower Roof xxx Hotel Building Plot No. :           xxx Location:           Al Barsha 1st, Dubai, UAE Client:                xxx Consultant:       … Continue reading Regarding renewal of Permit for Building construction or Demolition

No Objection from xxx Contracting LLC (Main Contractor to release the shoring contracting deposits with RTA)

advance payment

Ref: xxx Date: xxx To, Right of way Authority Traffic control Section Dubai, UAE Project:             2B+G+14+Lower Roof xxx Hotel Building Plot No. :           xxx Location:           Al Barsha 1st, Dubai, UAE Client:                xxx Consultant:       … Continue reading No Objection from xxx Contracting LLC (Main Contractor to release the shoring contracting deposits with RTA)

Request for permit to place minor road diversion to place concrete pump in front of the plot

Road Block

Ref: xxx Date: xxx To, Right of way Authority Traffic control Section Dubai, UAE Project:             2B+G+14+Lower Roof xxx Hotel Building Plot No. :           xxx Location:           Al Barsha 1st, Dubai, UAE Client:                xxx Consultant:       … Continue reading Request for permit to place minor road diversion to place concrete pump in front of the plot

Requirement of Anti Carbonated Paint System details for tomorrow’s meeting

Textured Anti Carbonated

Date: xxx Ref. xxx To:                    Project:              2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Subject:           Requirement of Anti Carbonated Paint System details for tomorrow’s meeting Dear Sir, With ref. to above, there is meeting held tomorrow dt.25.07.16 at 2:00PM where you have to bring… Continue reading Requirement of Anti Carbonated Paint System details for tomorrow’s meeting

Regarding Light Textured Anti Carbonated Paint System for the basement and our previous submittal

Textured Anti Carbonated

Date: xxx Ref. xxx To:                    Project:              2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Subject:             Regarding Light Textured Anti Carbonated Paint System for the basement and our previous submittal. Dear Sir,      With ref. to above our painting proposal which is submitted on 18.4.16… Continue reading Regarding Light Textured Anti Carbonated Paint System for the basement and our previous submittal

previous ref: CC/STSTYLE/001 & attachment of the new balance item sheet. (Kindly ignore previous sheet attached)

Office checks forms, priority list checks, check mark list and checking paper to do checklists.

Date: xxx Ref. xxx To          :              xxx Building material Supply                             Tel-xxx Kind Attn            : The Manager Project                   : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject:  previous ref: CC/STSTYLE/001 & attachment of the new balance item sheet. (Kindly ignore previous sheet attached) Dear Sir,… Continue reading previous ref: CC/STSTYLE/001 & attachment of the new balance item sheet. (Kindly ignore previous sheet attached)

Verbal intimation by client that you are nomination to supply that balance item from our list attached for our above project

Office checks forms, priority list checks, check mark list and checking paper to do checklists.

Date: xxx Ref. xxx To          :              xxx Building material Supply                             Tel-xxx Kind Attn            : The Manager Project                   : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject:  Verbal intimation by client that you are nomination to supply that balance item from our list attached for… Continue reading Verbal intimation by client that you are nomination to supply that balance item from our list attached for our above project

Regarding serious issue of reduction of slump at pumping point and slab level as well as blockage of the pipeline and other issues

Concrete Slump Test

Date:xxx Ref No. xxx To                    : M/s xxx Project             :2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject           : Regarding serious issue of reduction of slump at pumping point and slab level as well as blockage of the pipeline and other issues Dear Sir, With reference to… Continue reading Regarding serious issue of reduction of slump at pumping point and slab level as well as blockage of the pipeline and other issues

To provide CCTV approved drawing from authority to remove the special condition from the original permit prior to BCC

CCTV Camera

Date: xxx                   Ref. xxx To                  :  M/s. xxx Communication DMCC Project         :  2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at                         Al   Barsha 1st, Dubai, U.A.E. Client         :   Mr. xxx Subject :  To provide CCTV approved drawing from authority to remove the special condition from the… Continue reading To provide CCTV approved drawing from authority to remove the special condition from the original permit prior to BCC