Notice of Delay in Payments

xxx Club Delivery of Cabinets / Delay Notice

Our Ref: xxx

Date: xxx

To                    :           xxx International Contracting LLC

                                    P. O. Box xxx

            Dubai, U.A.E.

            Tel: xxx

            Fax: xxx

Attention          :           Mr. xxx

Email               :           xxx

Project             :           xxx Polo Club

Subject            :           xxx Club Delivery of Cabinets / Delay Notice

Dear Mr. xxx,

We refer to your 5th Revision schedule on the deliveries of Polo Club cabinets where the completion date was on 29th of September xxx.

The below is the current status on the deliveries.

Villa TypeTotal QuantityDelivered so farPending QuantityCompletion Due Date
SDT2260 Units223 Units37 Units24th September xxx
SDT1192 Units0 Units192 Units29th September xxx
SB 120 Units0 Units120 Units29th September xxx
Total572 Units223 Units349 Units

We are not getting any feedback on the deliveries from your end and no action plan to compete the above mentioned project. Due to the default on deliveries/ delays we are unable to claim our money from the client for the work we had done. As mentioned in our previous correspondences this will lead to damages & penalties and the same will be back charged to xxx Interiors.

We urge you to take immediate action to complete the deliveries at the earliest to reduce the impact on your damages.

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager