Keys Handing over

Reply for Letter Unipods 186 (Delay of Works)

Ref                                         : XXX/1437/XXX-050

Date                                      : 03th July XXX

To                                           : XXX ENGINEERING AND CONTRACTING

Attention                            : Mr. xxx

Project                                 : XXX STAFF ACCOMADATION

Subject                                 : Reply for Letter Unipods 186 (Delay of Works)

Dear Mr. xxx,

Please be informed that xxx haven’t got any official MEP clearance from xxx Engineering to complete our false ceiling works in the pods. The materials and work force is already available at site. From the meeting yesterday with the client and consultant representatives it was clear that xxx clearance above the ceiling for the Plot OAS 006, Block 4 is on 28th of January. So there is no delay from xxx site so far in the work progress.

Below mentioned are the dates given to Unipods as clearance confirmation from Al Hani.

PLOT 006         Block 4            28th      January            xxxx

                        Block 3            28th      January            xxxx

                        Block 6            29th      January            xxxx

                        Block 5            31st      January            xxxx

                        Block 2            03rd      February          xxxx

                        Block 1            07th      February          xxxx

Any false ceiling removed from our pods after the works are finished, xxx cannot take the responsibility for the damages and cleaning.

Hope you understand and will do the needful.

Regards,

xxx

Projects Manager