Date: xxx.
Ref.: xxx
Total Pages: 1
To,
Mr. xxx
The Owner
Project: Proposed G+1 Private Villa for Mr. xxx,
On Plot No. xxx At Nad Al Shiba First, Dubai, UAE.
Subject: Received Compliance Notice – V-xxx Plot no:xxx
Reference: Emailed received from DDA- Subj: Compliance Notice – V-xxx Plot no: xxx & xxx/OWNR/010/2020 dated 22nd November 2020
Dear Sir,
This is further to the DDA site violation notice V-xxx, we have submitted to DDA portal as compliance photos shared by you. DDA has rejected the compliance statement with following comments.
S.No | Observations | Remarks |
1 | Absence/Use of unsafe protective barriers to protect workers and materials from falling | Failure to implement safe work systems for height works https://dda.gov.ae/wp-content/uploads/2019/12/Circular-339.pdf |
2 | Absence/Use of unsafe protective barriers to protect workers and materials from falling | Failure to implement safe work systems for height works https://dda.gov.ae/wp-content/uploads/2019/12/Circular-339.pdf |
3 | No work at the site | Please update the project status |
Please note that DDA is giving us 2 working days to give the final response regarding the violations.
Kindly do the needful to respond to DDA and close it out.
Yours Sincerely,
xxx Building Contracting LLC