Received Resolution Notice – V-xxx Plot no: xxx

Received Resolution Notice – V-xxx Plot no: xxx

Date: xxx.

Ref.: xxx

Total Pages: 1

To,

Mr. xxx

The Owner

Project:          Proposed G+1 Private Villa for Mr. xxx,

On Plot No. xxx At Nad Al Shiba First, Dubai, UAE.

Subject:              Received Resolution Notice – V-xxx Plot no: xxx

Reference:         Emailed received from DDA- Subj: Resolution Notice – V-xxx Plot no: xxx & xxx/xxx/OWNR/011/2020 dated 25th November 2020

Dear Sir,

This is further to the DDA site violation notice V-xxx; we have received again a notification from DDA since you have failed to comply with their observations notified to us on 25-Nov-2020.

DDA sent the below Resolution notice, to ensure compliance with the following observation(s).

S.NoObservationsRemarks
1Absence/Use of unsafe protective barriers to protect workers and materials from fallingPlease provide closure comments as per approved risk assessment related to the captured observation along with corrective action and photo evidence. Refer to DM Code of construction safety practice
2Absence/Use of unsafe protective barriers to protect workers and materials from fallingPlease provide closure comments as per approved risk assessment related to the captured observation along with corrective action and photo evidence. Refer to DM Code of construction safety practice
3No work at the sitePlease update the project status

Please note that DDA request you to comply with the Resolution notice before 02-Dec-2020.

Kindly do the needful to respond to DDA and close it out. Please note fail to comply with comments will lead penalty this time and you will be sole responsible to pay including MCM coordination charge mentioned earlier.

Yours Sincerely,