Notice of Delay in Payments

Reply – Notification of Delay

Ref: xxx

Date: February 18, xxx

To,

xxx ARCHITECTURAL & ENGINEERING CONSULTANCY
Office No. xxx, Sobha Ivory 2, Business Bay

P.O. Box xxx, Dubai, UAE

Project: Residential Villa (G+1) & Pump Room Block, On Plot No. 6xxx at Al Barari – Dubai, UAE for Mr. xxx

Subject: Reply – Notification of Delay

Dear Sir,

This is further to your letter ref. AAEC/DB/3244/22/AS dated 15th February xxx, most of the items has submitted and under engineering approval process. The balance three items will be submitted within next week. Following are MCM response.

SLATRIUM COMMENTSMCM RESPONSE
1Submission of MDB, DB and SMDB: Negative 6 days.Supplier and manufacture prequalification under review, will be submitted by 18th February xxx.
2Submission of water transfer pump sets: Negative 75 daysAlready approved from PDP
3Submission of sump pump: Negative 73 daysAlready approved from PDP
4Submission of booster pump: Negative 69 daysAlready approved from PDP
5Submission of circulation pump: Negative 69 daysAlready approved from PDP
6Submission of GRP panel water tank: Negative 49 daysSubmission is under review, will be submitted by 20-Feb-xx
7Submission of FCU: Negative 49 daysSubmitted on 17-Feb-xx.
8Submission of variable refrigerant unit: Negative 56 daysSubmitted on 17-Feb-xx
9Submission of exhaust fan: Negative 49 daysUnder review, will be submitted by 22-Feb-xx.

We would like to highlight that, despite of multiple obstruction from authority, neighbor for the swimming dewatering work, we have recovered the delay and now it’s almost 0 float for construction activity. The delay in engineering submission and approval will also be recovered soon.

Yours Sincerely,           

MCM LLC