Date: xxx
Reply – Notification of Delay
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject: Reply – Notification of Delay
Dear Sir,
This is further to your letter ref. AAEC/DB/3244/22/AS dated 15th February 2022, most of the items has submitted and under engineering approval process. The balance three items will be submitted within next week. Following are the MMC response.
| SL | ATRIUM COMMENTS | MCM RESPONSE |
| 1 | Submission of MDB, DB and SMDB: Negative 6 days. | Supplier and manufacture prequalification under review, will be submitted by 25th February 2022. |
| 2 | Submission of water transfer pump sets: Negative 75 days | First revision was submitted on 20-Jan-22 and resubmitted on 10- Feb 22 as per consultant comments. |
| 3 | Submission of sump pump: Negative 73 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
| 4 | Submission of booster pump: Negative 69 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
| 5 | Submission of circulation pump: Negative 69 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
| 6 | Submission of GRP panel water tank: Negative 49 days | Submission is under review, will be submitted by 22-Feb-22. |
| 7 | Submission of FCU: Negative 49 days | Submitted on 17-Feb-22. |
| 8 | Submission of variable refrigerant unit: Negative 56 days | Submitted on 17-Feb-22 |
| 9 | Submission of exhaust fan: Negative 49 days | Under review, will be submitted by 25-Feb-22. |
We would like to highlight that, despite of multiple obstruction from authority, neighbor for the swimming dewatering work, we have recovered the delay and now it’s almost 0 float for construction activity. The delay in engineering submission and approval will also be recovered soon.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager
EngineersBlog Home | Reply – Notification of Delay – Reply – Notification of Delay
{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Reply – Notification of Delay – Reply – Notification of Delay”, “description”: “We would like to highlight that, despite of multiple obstruction from authority, neighbor for the swimming dewatering work, we have recovered”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-02-17T17:12:19+04:00”, “dateModified”: “2022-02-17T17:12:25+04:00”, “url”: “https://engineersblog.net/reply-notification-of-delay/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Contractor’s Letters”, “item”: “https://engineersblog.net/contractors-letters/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Reply – Notification of Delay – Reply – Notification of Delay”, “item”: “https://engineersblog.net/reply-notification-of-delay/” } ] }