Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha
1st, Dubai U.A.E.
Subject : Required Engr. Instruction for the AC Opening in Lift Wall
Dear Sir,
With reference to above mentioned subject, we are awaiting your formal instruction to provide the opening of AC ( 8”X 8”) size pipe sleeve as discussed in meeting held to your office last Jan. 21, 2017 ( Saturday) for Lift Shaft. Kindly issue the formal Engineer’s Instruction on approved Lift Shop Drawing and this proposed opening should not be an obstruction for the Lift Sub-Contractor equipment shifting or installation.
This is only for your kind information and record.
NOTE: If no further Engineer’s Instruction received we will close all the sides of Lift Shaft.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager