Reply - Notice of Delay

Issue of MEP  (Formal reminder)

Date: xxx

Ref. xxx

Kind Attn:     Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotels Building

Plot No.:          xxx at Al Barsha 1st, Dubai

Subject    :     Issue of MEP  (Formal reminder)

Dear Mr.Tahir,

With reference to the above mentioned subject please find the followings.

  1. Revised Corridor coordination drawing not yet submitted. We have issue of time extension delayed by since last 30 days (Ceiling drawing rejected on xxx).
  2. Pump room foundation issues not yet resolve and work under hold.
  3. Fire hose cabinet issue pending since 6 months (Work under hold).
  4. Level confirmation and services coordination for the Ground floor and 1st floor, we are facing reminders from consultant and issue of the handing over (Serious issue).
  5. 2nd floor toilet not yet handover to start tiling and waterproofing work.
  6. Floor tiling under hold at 2nd floor (We can’t make mock up floor and can’t shift office).
  7. Interior did not have full toilet clearance.
  8. Doorbell drawings not submitted and affect the partial clearance. (Impact in Partition work).
  9. Clearance to the joinery only in Room no 1, 2, 3 balance rooms not yet handed over (Complain from Interior).
  10. Unit no 4, 7, 8,9,10 still MEP not give clearance.
  11. Air cooling fan not available.
  12. Big fan already order for working area and MEP team cannot work without fan it’s create the problem for work Progress. (No progress due to fan issue).
  13. Tiling work under hold at basement due to urinal shop drawing rejection and resubmission.

Regards,

For xxx Contracting L.L.C

xxx

General Manager                      