Date: xxx
Ref. xxx
To : M/s xxx Trading Company
Project : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai
Sub : Not to fix pool tile as we instructed to your foreman before water proof
Dear Mr. Pravinder
We are hereby inform you we instructed to your foreman not to do water proof for pool tile and do not fix the tile since we have to following activities:
- Cradle fixing and removal for external plaster/paint at pool area parapet
- Inside parapet tile above pool and paint of pool area parapet with scaffolding erection for height in the pool itself
So we will not allow you to fix the tile in pool floor and wall and your foreman agree the same but now you are started the tile process, stop immediately and we give our program and we will inform when you need to fix tile at pool that will be in the month of March 2018
This is for your kind information and not to proceed for tiling as we inform your foreman and his confirmation.
For xxx Contracting L.L.C
xxx
Project Manager