xxx Architects & Engineers, Ref No: – xxx/PROJ/YAH/18/077 PO Box No -112994 October 17, xxx
Dubai, UAE
Project: Construction of G+1 villa for Mr. Yousef Al Hashimi on plot No. 672-161 at Al Barsha South Second
Attention: Mr. xxx
Subject: Nomination/approved quotation
Dear Sir,
With Regards to the above-mentioned project and subject, we are in receipt of Low current works Quotation from ……. without Consultant/Client approval.
We request you to provide us official Subcontractor nomination or at least approve the quotation signed by client and consultant with details of work scope to facilitate subcontractor agreement as aforesaid item is under Provisional Sum.
We also like draw your attention for the following Subcontractor nomination:
- Wooden Works (doors, Kitchen Cabinet, Wardrobes, Vanity Counters)
- Light Fittings, Switch and Sockets
- Garage Door and Pedestrian Door
- Cat Ladder
- Sky Light
- Mirrors
Therefore, we request you to issue aforesaid Subcontractor nomination/approved quotation at the earliest to meet the project completion date.
Yours in Trust,
xxxLLC