COMMMMISSIONING CERTIFICATE

To provide Third Party Certificate documents for structural inspection as Per Civil Defense requirements

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject           : To provide Third Party Certificate documents for structural inspection as                           Per Civil Defense requirements and their accreditation license and your contract with […]

To provide Third Party Certificate documents for structural inspection as Per Civil Defense requirements Read Post »

Central Gas System

Regarding newly issued revised DCD drawing for LPG tank at 1st floor

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding newly issued revised DCD drawing for LPG tank at 1st floor Dear Sir, With reference to above, we would like to intimate

Regarding newly issued revised DCD drawing for LPG tank at 1st floor Read Post »

demobilizing

Intimation to remove the temporary office from the 1st floor to handover the area.

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Intimation to remove the ply room from the 1st floor to handover the area. Dear Sir, With reference to above, we would like

Intimation to remove the temporary office from the 1st floor to handover the area. Read Post »

Reply - Notice of Delay

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject         : Disagree with your reply and issue not addressed. Dear Sir, With reference to above, we would like to inform you at we disagree

Read Post »

Slow Progress

Regarding slow progress and awaited reply for ref no. xxx dtd: xxx as well as invoice issue.

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding slow progress and awaited reply for ref no. CC/METALU/17 dtd: 05-07-2017 as well as invoice issue. Dear Sir, With reference to above,

Regarding slow progress and awaited reply for ref no. xxx dtd: xxx as well as invoice issue. Read Post »

The Engineers

Regarding issue of the DCL inspector and advance requirement by them.

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding issue of the DCL inspector and advance requirement by them. Dear Sir, We would like to inform you yesterday DCL inspector visited

Regarding issue of the DCL inspector and advance requirement by them. Read Post »

Letter Sample

Regarding consultant letter Ref: xxx handing over the door handle sample (Model No: E232Z1) &Main entrance door finishes.

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding consultant letter Ref: AP/269/CC/362 handing over the door handle sample (Model No: E232Z1) &Main entrance door finishes. Dear Sir, With reference to

Regarding consultant letter Ref: xxx handing over the door handle sample (Model No: E232Z1) &Main entrance door finishes. Read Post »

Site Meeting

submission of compliance statement of consultant comments on Shop drawing (Approved as Noted)

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding submission of compliance statement of consultant comments on Shop drawing (Approved as Noted) Dear Sir, With reference to above, Aluminum and Glazing

submission of compliance statement of consultant comments on Shop drawing (Approved as Noted) Read Post »

Aluminium & Glazing works

To fox window at unit nos. 5 and 6 from 2nd to 3rd floor for contact  

                           position and eliminate any risk. Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            :To fox window at unit nos. 5 and 6 from 2nd to 3rd floor for contact                            

To fox window at unit nos. 5 and 6 from 2nd to 3rd floor for contact   Read Post »

CVI

non-submission of structural calculation and commented shop drawing comply with consultant comments

Date: xxx Ref. xxx To:                     M/s. xxx , Metal Wowks Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject            : Regarding non-submission of structural calculation and commented shop drawing comply with consultant comments. Dear Sir, With reference to above mentioned subject, as structural

non-submission of structural calculation and commented shop drawing comply with consultant comments Read Post »